| Dag | Beskrivelse | Tid Start | Timer/hrs | Tidbank Tid |
| 01 | Time registration administration for Jan and Feb 2009. | | | |
| | Set up personal time accounting for fjerntilknytning. | | | |
| | Update, build and test of Qc2 on work machine. | 17:00 | 3 | 20090302 1500-1800 |
| 02 | | | | |
| 03 | Prepared a draft NORDKLIM OBS Project Plan | | | |
| | Qc2 Development: work on test tools to support remote operations | 21:00 | 3 | 20090303 1500-1800 |
| 04 | Qc2 Development: configuration rule development for controlflags | 16:00 | 3 | 20090304 1600-1900 |
| 05 | Qc2 Development: time series interpolation. | 12:00 | 2 | 20090306 1200-1400 |
| | | | | 20090305 7:45 AV |
| 06 | - | - | - | - |
| 07 | - | - | - | - |
| 08 | Qc2 Development: algorithm performance testing | 10:00 | 6 | 20090309 0900-1500 |
| 09 | Qc2: Review and analysis of kv2kl as a data input proxy for | - | - | - |
| | kvalobs test environment including teleconference with Terje | 17:00 | 3 | 20090309 1500-1800 |
| 10 | Qc2: Trouble-shooting old algorithms and running on new platform. | - | - | - |
| | Regeneration of test data. | 21:00 | 3 | 20090310 1500-1800 |
| 11 | - | - | - | - |
| 12 | Qc2: Testing of interpolation suite. General Qc2 work. | 16:00 | 4 | 20090311 1000-1200 |
| 12 | | | | 20090312 1000-1200 |
| 13 | - | - | - | - |
| 14 | Qc2: Prepapration of statistics plotting functions. | 09:00 | 3 | 20090313 1400-1700 |
| 15 | Qc2: General work. Tuning of configuration file parameters. | 16:00 | 4 | 20090316 1200-1600 |
| 16 | Trouble-shooting kv2kl daemon. | - | - | - |
| | General administration. | 20:00 | 3 | 20090317 1200-1500 |
| 17 | - | - | - | - |
| 18 | Teleconference. Qc2 algorithm development. Generation ofadditional test data. | 17:00 | 4 | 20090318 1200-1600 |
| 19 | Qc2: Rebuild Kvalobs database with new test data. | 16:00 | 2 | 20090319 1800-2000 |
| 20 | - | - | - | - |
| 21 | Worked through and applied GNU autoconfig and automake utilities. | 08:00 | 4 | 20090320 1200-1600 |
| 22 | Development of postscript plotting routines to support algorithm tests and documentation. | 08:00 | 4 | 20090323 0800-1200 |
| 23 | - | - | - | - |
| 24 | Continuation with new plotting routines. | 12:00 | 3 | 20090324 1200-1500 |
| 25 | Teleconference. Continuation with new plotting routines. | 12:00 | 2 | 20090325 1700-1900 |
| 26 | Continuation with new plotting routines. | 12:00 | 3 | 20090326 0900-1200 |
| 27 | - | - | - | - |
| 28 | Qc2 Algorithm development. | 15:00 | 3 | 20090327 0800-1100 |
| 29 | Integration of plotting routines for algorithm testing. | 18:00 | 3 | 20090327 1100-1400 |
| 30 | Trouble shooting of postscript utilities for kvalobs algorithm analysis. | 22:00 | 3 | 20090330 1100-1400 |
| 31 | Built virtual machine and began kvalobs installation. | 16:00 | 4 | 20090331 1600-2000 |
| | Provided QC-feedback on documentation and build experience. | - | - | - |