Differences

This shows you the differences between two versions of the page.

Link to this comparison view

Both sides previous revision Previous revision
Next revision
Previous revision
kvalobs:kvoss:system:qc2:8hdk376snf09zj37dk82s92:201001 [2010-01-18 01:08:05]
paule
kvalobs:kvoss:system:qc2:8hdk376snf09zj37dk82s92:201001 [2022-05-31 09:29:32] (current)
Line 9: Line 9:
 |06 |Administration. Reset test environemnt after ferien. |18:00 |2 |20100106 1800-2000 | |06 |Administration. Reset test environemnt after ferien. |18:00 |2 |20100106 1800-2000 |
 |07 |Investigation and documentation of issues on Qc2 Flags. Performed corresponding tests. Developed some quick tools to plot results. |12:00 |4 |20100107 1200-1600 | |07 |Investigation and documentation of issues on Qc2 Flags. Performed corresponding tests. Developed some quick tools to plot results. |12:00 |4 |20100107 1200-1600 |
-|08 |Writing Acceptance Test File and investigating kvalobslib kvDataFlag.cc code, turned on Qc2 parts. |10:00 ||20100108 1000-1400 |+|08 ||||- |
 |09 |- |- |- |- | |09 |- |- |- |- |
-|10 |- |- ||- |+|10 |Review of reorganisation material. IT-Group meeting. Update of qabase_cron.sh for dev-vm116 Qc2 configuration. |10:45 |3 |20100110 1045-1345 |
 |11 |Documentation work on Qc2 control flags. Teleconference. |16:00 |3 |20100111 1600-1900 | |11 |Documentation work on Qc2 control flags. Teleconference. |16:00 |3 |20100111 1600-1900 |
 |12 |Documentation work on Qc2 control flags |12:00 |4 |20100112 1200-1600 | |12 |Documentation work on Qc2 control flags |12:00 |4 |20100112 1200-1600 |
Line 19: Line 19:
 |16 |- |- |- |- | |16 |- |- |- |- |
 |17 |- |- |- |- | |17 |- |- |- |- |
-|18 ||||- | +|18 |Correspondence and administration. Maintenance of virtual machine servers. |22:00 ||20100118 1800-2000 
-|19 ||||- | +|19 |Development of useinfo flag checking tools. |12:00 ||20100119 1200-1600 
-|20 ||||- | +|20 |Flag checks and further documentation. Empirical tests. |08:00 ||20100120 0800-1200 
-|21 ||||- | +|21 |Prepapration for EUMETGRID meeting. |18:00 ||20100121 1600-2000 
-|22 ||||- |+|22 |Prepapration for EUMETGRID meeting. |16:00 ||20100122 0800-1600 |
 |23 |- |- |- |- | |23 |- |- |- |- |
 |24 |- |- |- |- | |24 |- |- |- |- |
-|25 |- |- |- |- | +|25 |On-site: Time registered in Tidbank directly. |- |- |- | 
-|26 ||||- | +|26 |Last day of EUMETGRID Workshop and Travel time. |09:00 |11 |20100126 0900-2000 
-|27 ||- |- |- | +|27 |AVSPASERING |- |- |- | 
-|28 |- |- ||- | +|28 |Review of reorganisation material. IT-Group meeting. Update of qabase_cron.sh for dev-vm116 Qc2 configuration. |10:45 |3 |20100128 1045-1345 
-|29 |- |||- |+|29 |Identification of test data, carry-out and documentation of Qc1/Qc2 Flag regression test. |12:00 ||20100129 1200-1600 |
 |30 |- |- |- |- | |30 |- |- |- |- |
 |31 |- |- |- |- | |31 |- |- |- |- |
  
  • kvalobs/kvoss/system/qc2/8hdk376snf09zj37dk82s92/201001.1263776885.txt.gz
  • Last modified: 2022-05-31 09:23:18
  • (external edit)