Dag | Beskrivelse | Tid Start | Timer/hrs | Tidbank Tid |
01 | Database management tasks on dev-vm116. Update of test environement code. EUMETGRID follow-up activities. | 08:00 | 4 | 2010-02-01 0800-1200 |
02 | Testing re-distribution code. Update of test data on development environment for operational tests. Investigate low incidence of corrections for operational windows. | 12:00 | 5 | 2010-02-02 1200-1700 |
03 | Flag specification work. Documentation | 21:00 | 3 | 2010-02-03 0800-1100 |
04 | First scrum. Testing redistribution options and interpolation choices. | 12:00 | 3 | 2010-02-04 1200-1500 |
05 | Various administrative activities and office maintenance. Analysis of kvalobs to do list. | 12:00 | 6 | 2010-02-05 1200-1800 |
06 | - | - | - | - |
07 | - | - | - | - |
08 | Kvalobs Kick-Off Meeting. Set up testing for different interpolation methods wrt precipitation conditions. | 15:00 | 3 | 2010-02-08 1500-1800 |
09 | Qc2 testing and documentation work. | 10:00 | 2 | 2010-02-09 1000-1200 |
10 | Trouble-shooting kvalobs Qc1 environment, set precipcollected_flag to be the algorithm running (food for Qc2). Review KO meeting minutes and notes. | 10:00 | 3 | 2010-02-10 1000-1300 |
11 | Short scrum (30 mins) and later teleconference. Analysis of requirements for debian package set up. Documentation of acceptance test file work. | 14:00 | 4 | 2010-02-11 1400-1800 |
12 | Flag documentation. Installation of Qt3/4 libraries on dev-vm116. Reconfigure algorithms to all run RANGE_CHECK in investigation of missing row generation. | 16:00 | 6 | 2010-02-12 0800-1400 |
13 | - | - | - | - |
14 | - | - | - | - |
15 | AVSPASERING | - | - | - |
16 | kvalobs interpreter discussion during Teleconferene. Investigation of database algorithm controls, Witi frameworks. Use of SeNorge to identify test data cases. | 16:00 | 4 | 2010-02-16 1600-2000 |
17 | Update and expansion of test environment. Trouble shoot missing lines in kvalobs database. Station params and obs_pgm checks. | 12:00 | 4 | 2010-02-17 1200-1600 |
18 | Work on Qc2 control flag configuration after input from the flag expert group. | 10:00 | 4 | 2010-02-18 1000-1400 |
19 | Weekly scrum. More analysis of SeNorge data. | 12:30 | 3 | 2010-02-19 1230-1530 |
20 | - | - | - | - |
21 | - | - | - | - |
22 | AVSPASERING | - | - | - |
23 | Analysis of SeNorge summary data. Various administration. Teleconference. Triangulation interpolation method work; check of coordinate transformations. | 16:00 | 3 | 2010-02-23 1600-1900 |
24 | Add best station options to Qc2 interpolation configuration, take input from a file listing of the best neighbours. Began work on regional separation of stations. Increase dev-vm116 capacity. | 08:00 | 6 | 2010-02-24 0800-1400 |
25 | Improvements to operational environment; missing rows and obs_pgm metadata. Rewrote and tested cron-jobs. Weekly scrum. | 12:00 | 4 | 2010-02-25 1200-1600 |
26 | Separating Qc2 distribution from kvalobs tree. Work on reconfiguration of autoconf tools. | 14:00 | 6 | 2010-02-26 1400-2000 |
27 | - | - | - | - |
28 | - | - | - | - |